ABSTRACT
The project covers a view and detailed explanation of the route survey which in chider reconnaissance surrey, theologize traversing and levelling operation as well as soil tests which includes compaction test, mechanical analysis, plastic and liquid limits and CBR test.The project also covers the design of pavement and the geometric design of the road way
TABLE OF CONTENT
TITLE PAGE
APPROVAL PAGE
DEDICATION
ACKNOWLEDGEMENT
ABSTRACT
TABLE OF CONTENT
CHAPTER ONE
1.0INTRODUCTION
1.1AIM OF THE PROJECT
1.2RECONNAISSANCE SURVEY
1.3FACTORS CONSIDERED IN RECONNAISSANCE SURVEY
1.4GEOMETRIC DESIGN
1.5FACTORS WHICH FAVOUR THE SELECTION OF A ROUTD OR ROAD ALIGNMENT
1.6SCOPE OF THE PROJECT
CHAPTER TWO
2.0LEVELLING
2.1EARTH WORK
2.2SECTIONING
2.3LONGITUDINAL SECTIONS
2.4CROSSECTIONS
2.5NEED FOR SECTIONS
2.6THE PURPOSE, USES AND IMPORTANCE OF LEVELCING
2.7 INSTRUMENT USED IN LEVELLING
2.8TERMINOLOGUES USED IN LEVELLING
2.9TYPES OF LEVECS
2.10FIELD LEVELLING OPERATION
2.11TABULATION OF LEVELLING RESULTS
2.12EARTH WORK COMPUTATION
CHAPTER THREE
3.0BRIEF DESCRIPTION OF THE THEODOLITE
3.1THEODOLITE TRAVERSING
3.2TRAVERSING INSTRUMENTS
3.3FIELD TRAVERSING OPERATION
3.4TRAVERSE PESULT / COMPUTATION
CHAPER FOUR
4.0COLLECTION OF SAMPLES
4.1LABORATORY SOIL TEST
4.2TYPES OF LABORATORY TEST TO BE CARRIED OUT
4.3COMPACTION TEST
4.4CALIFORNIA BEARING RATIO TEST
4.5COMPUTATION OF CBR TEST RESULTS
4.6MECHANICAL ANALYSIS
4.7COMPUTATION OF SCEVE ANALYSIS RESULTS
4.8AYTERBERGE LIMIT TEST
4.9LIQUID LIMIT TEST
4.10PLASTIC LIMIT TEST
4.11PAVEMET DESIGN
4.12RIGD PAVEMENT
4.13FLEXI BLE PAVEMENT
4.14GROUD USDEX METHOD OF MANAGEMENT DESIGN
4.15CBR METHOD OF PAVEMENT DESIGN
4.16DRAINAGE WORKS
CHAPTER FIVE
5.0CURVES
5.1SIMPLE CURVES
5.2COMPOUND CURVE
5.3REVERSE CURVES
5.4TRANSITION
5.5FUNCTIONS OF A TRANSITION CURVE
5.6SURPER ELEVATION
5.7CURVE ELEMENT AND FORMULAE
5.8STAGES OF WORK IN ACTUAL ROAD CONSTRUCTIOON EQUIPMENT USED FOR THE ACTURAL ROAD
5.9CONSTRUCTION
5.10RECOMMENDATION
5.11CONCLUSION
5.12BIBLIOGRAPHY